How do I register as a critical care or chronic condition electricity customer in Texas?
PUCT's steps: "Have your doctor fill out the PUCT-approved Application for Chronic Condition or Critical Care Residential Customer Status." "Have your doctor submit the completed form to your electric utility using the contact information listed on the form." "You will be notified by your electric utility if your application is approved or denied by mail, at the address listed on the form."
Last reviewed: 2026-11-10. Sources
This page describes what the rule and the agencies say. It does not say what applies to you.
Under the rule, whether a person is a Critical Care Residential Customer or a Chronic Condition Residential Customer is a physician's determination. This page does not decide who qualifies, and this page is not medical advice.
Source: PUCT, Chronic Medical Condition and Critical Care Electricity Consumers, retrieved November 10, 2026.
PUCT's page says: "If your electric provider is municipally owned or an electric cooperative, you should contact your utility to see what options are available to you."
These facts are as of the date shown and may have changed. The rule, the agency page, and your provider or utility are the current source.
Source: PUCT, Chronic Medical Condition and Critical Care Electricity Consumers, retrieved November 10, 2026.
PUCT's page says to follow these steps:
- "Have your doctor fill out the PUCT-approved Application for Chronic Condition or Critical Care Residential Customer Status."
- "Have your doctor submit the completed form to your electric utility using the contact information listed on the form."
- "You will be notified by your electric utility if your application is approved or denied by mail, at the address listed on the form."
PUCT's page also says: "This form is also available in Spanish."
Source: PUCT form, Application for Chronic Condition or Critical Care Residential Customer Status (form footer: "Revised 3/21/2020"), retrieved November 10, 2026.
The PUCT form says: "Chronic condition or critical care status does not guarantee an uninterrupted, regular, or continuous power supply."
The PUCT form also says: "designation as a chronic condition or critical care residential customer does not relieve a customer of the obligation to pay for electric service, and service may be disconnected for failure to pay."
The rule says: "Designation as a Critical Load Customer, Critical Care Residential Customer, or Chronic Condition Residential Customer does not guarantee the uninterrupted supply of electricity."
Use the form on PUCT's page: PUCT's medical condition page, and the PUCT form (PDF). The PUCT form directs questions to the customer's "transmission and distribution utility (TDU)". Read What is a TDU (utility) in Texas, and who delivers my power?
Source: 16 TAC §25.497, Public Utility Commission of Texas, effective 5/13/18, retrieved November 10, 2026.
The rule says: "the commission-approved application form must be submitted to the TDU by a physician, in accordance with provisions of this section."
The rule also says: "If the physician submits the form to the REP, the REP shall forward it to the TDU electronically no later than two business days from receipt of the form."
The rule says of retail electric providers: "A REP shall notify each residential applicant for service of the right to apply for Critical Care Residential Customer or Chronic Condition Residential Customer designation." It also says: "Upon a customer's request, the REP shall provide to the customer the application form for Critical Care Residential Customer and Chronic Condition Residential Customer designation."
Source: 16 TAC §25.497(a) and (e)(5), Public Utility Commission of Texas, effective 5/13/18, retrieved November 10, 2026.
The rule defines a Chronic Condition Residential Customer as: "A residential customer who has a person permanently residing in his or her home who has been diagnosed by a physician as having a serious medical condition that requires an electric-powered medical device or electric heating or cooling to prevent the impairment of a major life function through a significant deterioration or exacerbation of the person's medical condition."
It defines a Critical Care Residential Customer as: "A residential customer who has a person permanently residing in his or her home who has been diagnosed by a physician as being dependent upon an electric-powered medical device to sustain life."
On how long a designation lasts, the rule says of the chronic condition designation: "If that serious medical condition is diagnosed or re-diagnosed by a physician as a life-long condition, the designation is effective under this section for the shorter of one year or until such time as the person with the medical condition no longer resides in the home. Otherwise, the designation or re-designation is effective for 90 days." Of the critical care designation it says: "The designation or redesignation is effective for two years under this section."
On who decides, the rule says: "The TDU shall not challenge the physician's determination of the customer's status ..." The sentence continues in the rule.
Source: 16 TAC §25.497(e), Public Utility Commission of Texas, effective 5/13/18, and the PUCT form, retrieved November 10, 2026.
The rule says: "If the TDU has returned the form as incomplete or has not finished processing the form within two business days from receipt of the form, the customer shall be designated as a Critical Care Residential Customer or Chronic Condition Residential Customer on a temporary basis pending final designation by the TDU." It also says: "If the form is returned to the customer as incomplete, the temporary designation shall remain in effect for 14 days, after which the temporary designation shall expire and the application process must start over."
The PUCT form says: "Chronic condition or critical care status does not guarantee an uninterrupted, regular, or continuous power supply."
On incomplete forms, the rule says: "Reasons that a TDU shall consider a form incomplete for an application for Critical Care Residential Customer or Chronic Condition Residential Customer designation include the omission of the name of the person for whom the protection is sought, contact information, physician signature, the designation as a Critical Care Residential Customer or Chronic Condition Residential Customer, and medical board license number of the customer's physician."
Source: PUCT, Chronic Medical Condition and Critical Care Electricity Consumers, retrieved November 10, 2026.
PUCT's page lists these protections:
- "Notifications of interruptions or suspensions of your electric service"
- "Certain protections against suspension or disconnection of your electric service"
The rule says: "Designation as a Critical Load Customer, Critical Care Residential Customer, or Chronic Condition Residential Customer does not guarantee the uninterrupted supply of electricity." The PUCT form says: "Chronic condition or critical care status does not guarantee an uninterrupted, regular, or continuous power supply."
For the disconnection rules, read When can my electricity be disconnected for nonpayment in Texas?
This page does not say whether you or anyone in your home qualifies for either status; under the rule that is a physician's determination, and this page is not medical advice. The PUCT form, the rule, and your utility control.
Common Questions
The rule says: "the commission-approved application form must be submitted to the TDU by a physician, in accordance with provisions of this section."
PUCT's page says: "Have your doctor submit the completed form to your electric utility using the contact information listed on the form." The rule says: "If the physician submits the form to the REP, the REP shall forward it to the TDU electronically no later than two business days from receipt of the form."
The PUCT form says: "Chronic condition or critical care status does not guarantee an uninterrupted, regular, or continuous power supply." It also says: "designation as a chronic condition or critical care residential customer does not relieve a customer of the obligation to pay for electric service, and service may be disconnected for failure to pay."
The rule says of the critical care designation: "The designation or redesignation is effective for two years under this section." For the chronic condition designation it says: "Otherwise, the designation or re-designation is effective for 90 days." The rule gives a different period for a life-long condition; read (a)(3) in the rule.
PUCT's page says: "If your electric provider is municipally owned or an electric cooperative, you should contact your utility to see what options are available to you."
Related Questions
- When can my electricity be disconnected for nonpayment in Texas?
- How do I file a complaint about my electricity provider in Texas?
- What is a TDU (utility) in Texas, and who delivers my power?
- How does prepaid electric service work in Texas?
Automated estimate from your uploaded bill. Not a substitute for your actual bill; details may be misread.
Texas Electricity Price Updates
Short updates on average Texas electricity prices, with a few linked news stories on what moved them. Pick how often. We may add plan comparison. Join the waitlist to hear if we do.
Sources
- Chronic Medical Condition and Critical Care Electricity Consumers, Public Utility Commission of Texas, retrieved 2026-11-10
- Application for Chronic Condition or Critical Care Residential Customer Status (PUCT form, "Revised 3/21/2020"), Public Utility Commission of Texas, retrieved 2026-11-10
- 16 TAC §25.497, Critical Load Industrial Customers, Critical Load Public Safety Customers, Critical Care Residential Customers, and Chronic Condition Residential Customers, Public Utility Commission of Texas, retrieved 2026-11-10